PMP考试概要及习题解析第一章典型例题1.8 典型例题1.Important aspects of a product include the maintenance and on-going operations.They should._.A) be include as activities in the project WBSB) not be viewed as part of a projectC) be undertaken as separate projects under a mutual programD) not be broken our as separate phases in the project life cycle产品的重要方面包括维护和日常运作,它们应当 _.A)作为活动包含在项目的工作分解结构中B)不作为项目的一部分C)作为同一个项目集中的一个单独的项目D)不是从项目生命周期中分离出来的独立的阶段