.1.1.1. 空调水系统试压及冲洗方案Pipe pressure test and washing scheme of HVAC water system1.1.1.1. 系统试压:Pipe pressure test1). 主要机具Main machines and tools空压机、临时水管(软管),、压力表、试压泵、对讲机、数码相机、手电筒等。Air compressor, temporary water pipe (or hose), pressure gauge, pressure test pump, interphone, digital camera and torch, etc。2). 试压前的准备:Pressure test preparationa). 密封:检查管路所有部位的流量控制阀为开启状态,末端及排水部位阀门等封闭位置为关闭状态。Sealing: All flow control valves of pipelines shall be opened and terminals and drainage valves s