1A new project manager is planning a complex hardware installation project. The team consists of 13 people who are experts in their fields. The project manager does not want to micromanage the project. How far should he decompose the work?A. As small as possible because the work is complexB. As large as possible because he is dealing with expertsC. To 1000-hour tasks because he is dealing with expertsD. To about 80-hour tasks because it will make the work less complex1. 一个新项目经理正在规划一个复杂