精选优质文档-倾情为你奉上调试需要准备材料Material Preparations for Commissioning一、 准备情况(截止2015年4月1日前)Preparation (before 2015/04/01)1、 仪器准备:准备完毕,正在相关单位进行检定。Instruments :Already complete and waiting for inspection of related organization.2、 方案和调试大纲:吹管方案已经编写完毕,调试大纲正在编写中.Commissioning procedure and outline:Steam blowing commissioning procedures already finish. Commissioning outline and other commissioning procedures are in process. 3、 仪器运输:已确定运输方式。Instruments transportation:Have fixed the patte