1、1第一章 基 础 工 程1.1 场地平整S=(58+4)*(26+4)=1860m21.2 桩基人工挖土单桩:7.0*1/4*3.14*0.8 =3.517 m 3共计:1.3*578*3.517=2032.71 m 31.3 桩基础工程量J1:共 140 根1)混凝土工程量:V=3.14DHN/4=0.7854*0.8*0.8*7.0*140=492.60 m 32)钢筋:a. 主筋:G=12.8*12*0.888*140*1.02=1113.00Kgb. 箍筋:G=8.076*12.8*140*1.02=843.52 Kgc. 钢筋小计:1113.00+843.52=1956.52 KgJ
2、2:共 145 根1)混凝土工程量:V=3.14DHN/4=0.7854*0.9*0.9*7.0*145=550.70m 32)钢筋:a. 主筋:G=12.8*12*0.888*145*1.02=556.50Kgb. 箍筋:G=8.076*12.8*145*1.02=421.76 Kgc. 钢筋小计:556.50+421.76=978.26 KgJ3:共 145 根1)混凝土工程量:V=3.14D2HN/4=0.7854*0.8*0.8*7.0*145=550.70 m 32)钢筋:a. 主筋:G=12.8*12.13*0.888*145*1.02=3014.37Kgb. 箍筋:G=8.076
3、*12.8*145*1.02=2108.81 Kgc. 钢筋小计:3014.37+2108.81=5123.18 KgJ4:共 148 根1)混凝土工程量:V=3.14D2HN/4=0.7854*0.8*0.8*12.8.*148=580.70 m 32)钢筋:2a. 主筋:G=12.8*13*0.888*148*1.02=2411.50Kgb. 箍筋:G=8.076*12.8*148*1.02=1087.04 Kgc. 钢筋小计:2411.50+1087.04=3498.54 Kg桩基工程量总计:桩-混凝土:V=2032.71 m 3桩-钢 筋:G=69339 Kg3第二章 钢筋混凝土工程2
4、.1 地梁工程量模板:S=(2.1+3.0)*0.35*2*8+6.6*0.35*2*4+4.8*2*16*0.35+(3.0+2.1+1.5)*0.4*2*6+(3.0+2.1)*0.35*2*6+(3.3+2.4)*0.3*2*6+4.5*0.4*2*6+3.9*0.35*2*5+3.6*0.5*2*2+3.0*0.5*2*2=668.61 m3钢筋:DL1: 8 根a. 主筋:G=(3.0+2.1)*1.21*6*5.1*1.58*4*8=554.06Kgb. 箍筋:l=(0.3-0.06)+(0.35-0.06)*2-0.1=0.96n=(5.1-0.060)/0.20+1=25.2G
5、=0.395*l*n*8=72.81 Kgc.钢筋小计:554.06+72.81=626.87 KgDL2: 4 根a. 主筋:G=6.6*2.98*4+6.6*2.47*2+6.6*2.0*2+6.6*1.58*2*4=634.13Kgb. 箍筋:l=(0.3-0.06)+(0.35-0.06)*2-0.1=0.96n=(6.6-0.060)/0.20+1=31G=0.395*l*n*4=47.02 Kgc.钢筋小计:634.13+47.02=681.15 KgDL3: 6 根a. 主筋G=(3.0+2.1+1.5)*4*2.47+(3.0+2.1+1.5)*4*2.0+(3.0+2.1+1
6、.5*2* 1.58)*6 =833.18Kgb. 箍筋:4l=(0.3-0.06)+(0.4-0.06)*2-0.10=1.06n=(3.0+2.1+1.5)-0.60/0.20+1=31G=0.395*l*n*6=77.88 Kgc. 钢筋小计:833.18+77.88=911.06 KgDL4: 16 根a. 主筋:G=(4.8*4*1.21+4.8*2*2.0+4.8*4*1.58)*16 =1164.29Kgb. 箍筋:l=(0.3-0.06)+(0.35-0.06)*2-0.10=0.96n=(4.8-0.60)/0.20+1=18G=0.395*l*n*16=109.21 Kgc
7、. 钢筋小计:1164.29+109.21=1273.50 KgDL5:6 根a. 主筋:G=(3.0+2.1)*(2*2.0+2*1.21+2*1.58+4*1.58)*6 =486.54Kgb. 箍筋:l=(0.3-0.06)+(0.45-0.06)*2-0.10=1.16n=(3.0+2.1)-0.60/0.20+1=23.5G=0.395*l*n*6=65.98 Kgc. 钢筋小计:486.54+65.98=552.52 KgDL6:6 根a. 主筋:G=1.5*3*(3*2.0+5*1.58)*6=375.3Kgb. 箍筋:l=(0.3-0.06)+(0.45-0.06)*2-0.1
8、0=1.16n=(1.5*3-0.60)/0.20+1=20.5G=0.395*l*n*6=54.75 Kgc. 钢筋小计:375.3+54.75=430.05 KgDL7:6 根5a. 主筋:G=3.3*(8*1.21+4*1.58)*6 =316.8Kgb. 箍筋:l=(0.3-0.06)+(0.3-0.06)*2-0.10=0.86n=(3.3-0.60)/0.15+1=19G=0.395*l*n*6=38.73 Kgc. 钢筋小计:316.8+38.73=355.53 KgDL8: 6 根a. 主筋:G=2.4*(8*1.21+4*1.58)*6 =230.4Kgb. 箍筋:l=(0.
9、3-0.06)+(0.3-0.06)*2-0.10=0.86n=(2.4-0.60)/0.10+1=19G=0.395*l*n*16=38.73 Kgc. 钢筋小计:230.4+38.73=269.13 KgDL9: 5 根a. 主筋:G=3.9*(6*1.21+4*1.58)*5=264.81Kgb. 箍筋:l=(0.3-0.06)+(0.35-0.06)*2-0.10=0.96n=(3.9-0.60)/0.20+1=17.5G=0.395*l*n*5=34.13 Kgc. 钢筋小计:264.81+34.13=298.94 KgDL10: 2 根a. 主筋:G=(3.0+3.6)*(6*2.
10、98+2*3.85)*2=337.66Kgb. 箍筋:l=(0.3-0.06)+(0.5-0.06)*2-0.10=1.26n=(3.0+3.6)-0.60/0.15+1=416G=0.395*l*n*2=40.81 Kgc. 钢筋小计:337.66+40.81=378.47 Kg钢筋工程量总计:17209.233 Kg混凝土工程量:V=(2.1+3.0)*0.35*0.30*8+6.6*0.35*0.30*4+4.8*0.35*0.3*16+(3.0+2.1+1.5)*0.4*0.3*6+(3.0+2.1)*0.35*0.3*6+(3.3+2.4) *0.3*0.3*6+(1.5+1.5+1
11、.5)*0.4*0.3*6+3.9*0.35*0.3*5+3.6*0.5*0.3*2+3.0*0.5*0.3*2=106.2 m32.2 底层、二层柱、梁、楼板工程量计算2.2.1 柱-模扳:Z-1:18 根 b*h=0.45*0.45 h=4.35-0.45S=18*0.45*(4.35-0.45)*4=126.36 m 2Z-2:6 根 b*h=0.45*0.45 h=4.35-0.45S=6*0.45*(4.35-0.45)*4=42.12 m 2Z-3:8 根 b*h=0.45*0.45 h=4.35-0.45S=8*0.45*(4.35-0.45)*4=56.16 m 2Z-4:4
12、根 b*h=0.45*0.45 h=4.35-0.45S=4*0.45*(4.35-0.45)*4=28.08 m 2Z-5:2 根 b*h=0.5*0.5 h=4.35-0.45S=2*0.5*(4.35-0.45)*4=15.6 m 2Z-6:2 根 b*h=0.4*0.4 h=4.35-0.45S=2*0.4*(4.35-0.45)*4=12.48 m 2Z-7:2 根 b*h=0.4*0.4 h=4.35-0.45S=2*0.4*(4.35-0.45)*4=12.48 m 2 Z-8:2 根 b*h=0.5*0.5 h=4.35-0.45S=2*0.5*(4.35-0.45)*4=15
13、.6 m 2底层柱模板工程量总计:606.72m 27柱-钢筋:G=(52+42+25+19)*18+(52+39+85+66)*6+(24+18+151+93)*8+(113+96+291+598)*4+(87+112+79+67)*2+(107+143+89+47)*2=36541Kg柱-混凝土:V=0.45*0.45*(4.35-0.45)*36+0.5*0.5*(4.35-0.45)*4+0.4*0.4*(4.35-0.45)*4=107.4 m32.2.2 梁-模板 :S=(0.4*2+0.25)*3.3*10+(0.45*2+0.25)*5.1*12+(0.3*2+0.25)*4.
14、8*16+(0.35*2+0.25)*4.8*16+(0.45*2+0.25)*10.2*6+(0.4*2+0.25)*13.2*3+(0.3*2+0.25)*2.4*5+(0.3*2+0.25)*3.3*2=517.42 m2梁-钢筋:KL1: 8 根a. 主筋:G=5.1*(4*2.0+2*1.58+2*1.21)*8=554.064Kgb. 箍筋:l=(0.25-0.06)+(0.35-0.06)*2-0.10=0.85n=(5.1-0.06)/0.2+1=25.2G=0.395*l*n*8=69.84 Kgc.钢筋小计:554.064+69.84=623.904 KgKL2: 8 根a
15、. 主筋:G=3.3*8*3.85*8=813.12Kgb. 箍筋:l=(0.25-0.06)+(0.40-0.06)*2-0.10=0.96n=(3.3-0.06)/0.2+1=17.28G=0.395*l*n*8=54.61 Kgc. 钢筋小计:813.12+54.61=867.73 KgKL3: 8 根a. 主筋:G=3.6*(4*2.47+1*2.0+2*3.85)8=563.904Kgb. 箍筋:l=(0.25-0.06)+(0.45-0.06)*2-0.10=1.06n=(3.6-0.06)/0.2+1=18.7G=0.395*l*n*8=63.64 Kgc. 钢筋小计:563.9
16、04+63.64=627.546 KgKL4: 8 根a. 主筋:G=3.0*8(6*2.98+2*2.47+4*3.85)*8=917.28Kgb. 箍筋:l=(0.25-0.06)+(0.35-0.06)*2-0.10=0.86n=(3.0-0.06)/0.2+1=15.7G=0.395*l*n*8=43.482 Kgc. 钢筋小计:917.28+43.482=960.762 KgKL5: 8 根a. 主筋:G=2.1*(2*1.21+2*1.58+2*0.888)*8=123.581Kgb. 箍筋:l=(0.25-0.06)+(0.45-0.06)*2-0.10=1.06n=(2.1-0
17、.06)/0.2+1=11.2G=0.398*l*n*8=40.50 Kgc. 钢筋小计:123.581+40.50=164.082 KgKL6: 32 根a. 主筋:G=4.8*(5*1.58+1*1.21)*32=1399.296Kg9b. 箍筋:l=(0.25-0.06)+(0.45-0.06)*2-0.10=1.06n=(4.8-0.06)/0.2+1=24.7G=0.398*l*n*8=84.376 Kgc. 钢筋小计:1399.296+84.376=1483.672 KgKL7: 8 根a. 主筋:G=3.3*(2*0.888+3*1.58+2*2.0)*8=277.622Kgb.
18、 箍筋:l=(0.25-0.06)+(0.45-0.06)*2-0.10=1.06n=(3.3-0.06)/0.2+1=17.2G=0.398*l*n*8=60.751 Kgc. 钢筋小计:277.622+60.751=338.373 KgKL8: 10 根a. 主筋:G=2.4*(5*1.58+1*2.47)*10=248.88Kgb. 箍筋:l=(0.25-0.06)+(0.30-0.06)*2-0.10=0.76n=(2.4-0.06)/0.2+1=12.7G=0.398*l*n*10=39.322 Kgc. 钢筋小计:248.88+39.322=288.202 KgKL9: 6 根a.
19、 主筋:G=2.1*(2*0.888+2*2.0+2*2.47)*6=135.022Kgb. 箍筋:l=(0.25-0.06)+(0.40-0.06)*2-0.10=1.08n=(2.1-0.06)/0.2+1=11.2G=0.398*l*n*6=30.948 Kgc. 钢筋小计:135.022+30.948=165.971 Kg10KL10: 6 根a. 主筋:G=5.1*(3*2.0+2*2.47)*6=334.764Kgb. 箍筋:l=(0.25-0.06)+(0.50-0.06)*2-0.10=1.16n=(5.1-0.06)/0.2+1=26.2G=0.398*l*n*6=74.79
20、2 Kgc. 钢筋小计:334.764+74.792=409.56 KgKL11: 6 根a. 主筋:G=4.5*(4*2.0+4*1.58)*6=386.64 Kgb. 箍筋:l=(0.25-0.06)+(0.35-0.06)*2-0.10=0.86n=(4.5-0.06)/0.2+1=23.2G=0.398*l*n*6=49.288 Kgc. 钢筋小计:386.64+49.288=165.971 Kg钢筋总计:19097.19 Kg梁-混凝土:V=0.4*0.25*3.3*10+0.45*0.25*5.1*12+0.3*0.25*4.8*16+0.35*0.25*4.8*16+0.45*0.25*10.2*6+0.4*0.25*13.2*3+0.3*0.25*2.4*5+0.3*0.25*3.3*2 =105.975 m32.2.3 楼板:现浇楼板楼板-模板:S=6.6*(2.1+3.0+2.1+1.5+1.5)*2+4.8*(3.0+2.1+1.5)*8+3.3*(3.0+2.1+1.5*3)*2+2.4*(3.0+2.1+1.5*3)*2+4.8*(3.0+2.1+1.5*3) +3.0*3.9+3.6*(3.9+2.4+1.5)=1477m2