精选优质文档-倾情为你奉上项目采购管理练习题1、While completing a project, a worker strike in the sellerscity has resulted in the required deliverable being late. What is generally the BEST thing for the project manager to do? A. Extend the contract for the length of the delay. B. Remind the seller that they are under contract to complete the project by the due date or be in default on the project. C. Investigate ways to shorten other parts of the project in order to meet the selle